July 27, 2012

University Avenue Status Update: 7/27/2012

STATUS UPDATE
Planned work for the week starting Monday July 30, 1210.

Work

  • The project is in Stage 3 to prepare the median areas for Stage 4. Stage 4 is estimated to begin August 6th+/-. Median area work will consist of removals, storm sewer, grading, base, and temporary asphalt.
  • The Old Middleton on ramp to University Avenue will be closed for 2 weeks from Monday July 23rd at 5:30 AM through Sunday August 5th.

 

Traffic

  • The Old Middleton Road on ramp detour will be Whitney Way and Right onto University Avenue.
  • The project will maintain one lane of traffic in both directions on University Avenue.
  • Left turns will be maintained at the intersections only.

 

Businesses

  • All Businesses on University Avenue are open and have access by right turns from University Avenue and surrounding streets. Please plan your route to businesses so that you will only need to turn right into their driveways.
  • The next Businesses meetings will be at the construction field office located in the Mid Town Square at 6333 University Avenue, Suite 108, Middleton on Friday August 3rd, 17th, and 31st, 2012, 9:00 AM.

 

Pedestrians and Bikes

  • Most Bus Stops will be maintained or temporarily moved in the same vicinity.
  • One Pedestrian Crossing will be maintained at all signalized intersections.
  • An accessible route for bikes is being maintained for the full length of the project utilizing a combination of the existing path and sidewalk on the north side of University Avenue from Allen Blvd. to Capital Ave., and on the south side from Capital Ave. to Whitney Way.
  • Beginning July 9th, the pedestrian path from Whitney Way to Indian Hills Park will be detoured while the retaining wall is constructed. The detour is Whitney Way to Old Middleton Road to the Old Middleton Road off ramp. This closure is anticipated to be completed August 20th+/-.

PROJECT DETAILS
University Avenue (Segoe Road – Allen Blvd): Work is scheduled March 19 – October 26. The project includes: pavement replacement, curb & gutter replacement, spot sidewalk replacement, street lighting, traffic signals, storm sewer, sanitary sewer, water main, and pavement marking.

University Avenue will be reduced to one lane of traffic in each direction at all times for the duration of the project. Left turn bays will be maintained at all signalized intersections.

Delays are expected during the peak commuting times. Motorists are encouraged to use alternate routes as well as alternate forms of transportation during this project to help ease construction. Access to all business will be maintained at all times during the project.

Additional project information, including how to sign up for email alerts, can be found on the City’s website at the following link: https://www.cityofmadison.com/engineering/universityAvenue/segoeAllen.cfm

FOR MORE INFORMATION

Visit the Project Website.

Filed Under: City News

← Special this weekend at Monona Golf Course Nominations due for Heritage Tree Program →

Sign Up for Weekly Emails

Search the Site

Copyright © 2025 VanChaMasShe Neighborhood Association · Maintained with care by Streamline Studio